Project Update

Spring 2025

Sapawe camp has reopened, after spring break-up closures, and foundations works and assembly trials are schedule to start in June.

As of the end of April 2025:

Phase 1 Progress

Clearing

Geotech

Foundations

Anchor Installations

 

Looking Ahead.

  • Roadbuilding is expected to begin in mid-May (weather permitting)
  • Tower assembly is planned to start in mid-August
  • Tower erection will follow in October
  • Conductor stringing is scheduled to begin in December

 

 

 

 

 

 

 

 

 